The Forest High School Early Enabling/Demolition Works

PROJECT NAME
The Forest High School Early Enabling/Demolition Works
CLIENT
The Department of Education/School Infrastructure NSW.
PROJECT DURATION
12 Weeks
PROJECT VALUE
$2,800,000
No items found.

As part of The Forest High School relocation plan, The NSW Department of Education/School Infrastructure NSW engaged Antoun’s Construction to undertake the demolition of the existing McLeod House at 187 Allambie Road, Allambie Heights.

The work completed included:

  • Site establishment and security.
  • Removal and disposal of hazardous materials. Namely bonded and friable asbestos, lead paint and lead dust.
  • Air monitoring, reporting and associated clearance certificates.
  • Tree Removal & Tree Protection.
  • Demolition of the existing double brick building to ground level, including removal of footings.
  • Remediation of the site area
  • Levelling the site area in preparation for the main works contractor

Thank you!

Your message has been received!
Oops! Something went wrong while submitting the form.
1
2
3
4
1
"Antoun’s have provided a good standard of service and have adhered to the contract requirements. Antouns have been responsive in resolving coordination issues discovered and achieved a consistently high standards of workmanship throughout the demolition works."

School Infrastructure NSW

2
"Antouns Construction performed extremely well in all aspects of the project. Good Environmental management and monitoring, work health safety managed very well during the entire project. Also the contractor is very collaborative with the principal all time."

Transport for NSW

3
"Antoun’s have worked with a high level of collaboration and communication with the project team. This has been demonstrated through ongoing cooperation to resolve coordination issues.
Antoun’s have established and are implementing a WHS Management Plan which complies with the contract, including the relevant NSW Government Management Systems guidelines and legislative requirements. Antoun’s have kept the site clean and tidy, and free of safety hazards. There has been no lost time due to injury and a demonstrated commitment to the highest WHS standards and the safety of everyone on the site."

School Infrastructure NSW

4
"Antoun’s have complied fully with the EMP, legislative requirements and met the requirements of the contract. The site has been kept clean and tidy, with appropriate environmental controls regularly maintained."

School Infrastructure NSW